21 January
Mass Grading of Oak Knoll’s Phase 1 Area Completed
The mass grading of Oak Knoll’s Phase 1 area was completed in fall 2019 and the process to install the buried sewer and storm drain pipes to support this section of the new community is partially completed. However, because of the current wet season, the installation of this underground infrastructure is paused until drier weather conditions return in the spring.
Presently, no grading is taking place on the property due to a City of Oakland ordinance that prohibits grading during the rainy season, which is defined as October 15 through April 15. A system is in place to manage the rainfall on the Oak Knoll site.